High flow events have the potential to damage pipelines that cross stream channels, possibly contaminating runoff. A hydrologic analysis conducted during the design of the pipeline can help determine proper placement. Flood frequency and magnitude evaluations are required for pipelines that cross at the surface. There are several methods that can be used, including reconnaissance, physiographic, analytical, and detailed methods. The method used must be appropriate for the site’s characteristics and the objectives of the analysis. Channel degradation and scour evaluations are required for pipelines crossing below the surface. Proper analysis and design can prevent future pipeline damage and reduce repair and replacement costs.